Work is expected to begin by the end of the week on the final phase of a 36-inch sewer force main replacement beneath U.S. Highway 17 in Myrtle Beach.

The work will close the two inside lanes of U.S. 17 southbound, as well as the median, around Restaurant Row from Chestnut Road to the U.S. 17 split with Kings Highway, according to a press release. Northbound lanes will not be affected.

The speed limit through the entire construction zone, northbound and southbound, will be decreased to 35 miles per hour.

The southbound lane closures will be in effect 24 hours a day for about three months, though much of the work will occur at night, Monday through Friday.

The project will cost about $2.9 million and will replace a 30-inch line that is 30 years old, according to the release.

Traffic control devices are being installed Tuesday and Wednesday and work will begin later this week.

Contact MAYA T. PRABHU at 444-1722 or follow her at Twitter.com/TSN_MPrabhu.

Myrtle Beach Sun News is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.